Single Window Service
Estate Officers under single window system would extend following facilities within the given time frame:
S.No. | Kind of Services | Time limit (working Days) |
1. | Permission To sell after conveyance deed | 15 |
2. | Permission to transefer the plot/house/ commercial site | 15 |
3. | i. Issue of conveyance deed | 15 |
ii.Issue of no due certificate | 07 | |
iii. Issue of copies of documents | 05 | |
4. | Change of ownership letter after sale deed | 05 |
5. | i.Change of ownership as a consequence of death of owner of site/house/plot (Registered Will) | 45 |
ii.Change of ownership as a consequence of death of owner of site/house/plot ( Un-registered Will) | 45 | |
iii. Change of ownership as a consequence of death of owner of site/house/plot ( On production of Legal Heir Certificate) | 10 | |
6 | Permission to mortgage | 10 |
7. | Sanction of building plans | |
i. Plots size below 500 Sq. Yards | 30 | |
ii. Plots size above 500 Sq. Yards | 60 | |
8. | Certificate of Registration as an Estate Agent | 05 |
9. | Certificate of Registration as a Promoter | 05 |
10. | Sanction of Sewerage Connection | 05 |
11. | Permission to occupy the building/ Completion Certificate | 15 |
12. | NOC/Allotment/ Copy of Re-allotment letter | 21 |
13. | Transfer of letter of intent | 20 |
14. | Permitting professional consultancy services | 05 |
* incase of non-compliance, please meet concerned EO or ACAs on the appointed day i.e. every Monday of the Week.
** for detail please refer to detailed brochures on the subject
Note:
In case of transfer of property or transfer of ownership on the basis of GPA or registered/un-registered Will, time period shall be 45 days.
(A) Residential
1. | Plot up to 10 Marla | Rs 1000/- |
2. | From 10 Marla to 16 Marla | Rs 2500/- |
3. | Above 16 Marla | Rs 5000/- |
4. | Group Housing | Rs 1000/ Flat/DU |
5. | Boundary wall only | Rs 1000/ Acre or part thereof |
(B) Commercial
i. | Booths | Rs 2500/- |
ii. | Single Story Shop | RS 5000/- |
iii. | SCO/SCF | Rs 20,000/- |
iv. | Individual Site, Multiples | @Rs 25,000/ Acre or part thereof |
v. | Boundary wall only | @ Rs 1000/
-do- |
(C) Institutional
i. | Govt. offices/ Govt. aided Educational Charitable & Religious institutions | @ Rs 10000/-
-do- |
iii. | Boundary wall | @ Rs 1000/-
-do- |
iv. | Other offices/ institutions/ Educational Non Charitable Institutions | @Rs 25,000/ Acre or part thereof |
v. | Boundary wall | @ RS 1000/
-do- |
Note:
1) This amount is refundable on taking completion certificate from PUDA.
2) No security would be required to be deposited in case of institutions where land allotted so free of cost.
Details of Security Fee (Non- Refundable)
a) In case of fresh plans:-
I ) @ RS 2.50 per sq. ft. of total covered area for residential use
II) @ RS 5 per sq. ft. of total covered area for other uses.
III) Construction of boundary wall @ 2.50 per running feet for all buildings excluding residential plots up to 2 kanal category specified in (I) above RS 5 per running feet for buildings mentioned in (II) above.
(b) In case of revised/ superseded plans, the fee charged shall be 50% (half) of the rate to be charged for fresh plans for such category of plots as mention in (I),(II)&(III) above.